Clubhouse Update
Posted on Aug 23rd, 2023
Work is continuing in the Clubhouse. The kitchen cabinets are in. Most if not all of the wood work is done. We are getting very close to the time when we can open up some rooms of the clubhouse for some evening events, and close to when we can open up entirely - day and evening - except for the kitchen.
We will let the groups currently scheduled for specific evening activities know when they are free to use the room that they normally use, and whether there are any specific limitations on the use of that room. The great room and craft rooms will likely be the last to open. Be aware that the rooms may not be totally finished: there could be materials stored in the room, and there may be more work to be done. Schedules and activities of the contractors will take precedence over any regular scheduled activity, and a room could be closed with very short notice
The pool and spa remain closed. The finance advisory committee and the board have approved work on the pool dehumidifier. The repair will include a new compressor and refrigerant. We will sign a work order / contract early this week. The contractor has indicated that the work could be done during mid-September. We are also attempting to schedule the painting of the pool deck, and the installation of additional railing in the pool.
No Comments